DOTr, JICA and PNR inspect NSCR Balagtas Station and Malanday Depot

2024/7/19 英字

The Department of Transportation (DOTr), Philippine National Railways (PNR), and Japan International Cooperation Agency (JICA) inspected Thursday the North-South Commuter Railway (NSCR) Balagtas Station and Malanday Depot.

The Balagtas station is reported to be 93.67 percent complete, while the Malanday depot stands 72.10 percent complete, as of June.

Transportation Secretary Jaime Bautista first inspected the Balagtas station in Bulacan, which features a roofing membrane known for its resistance to high temperature, chemicals, corrosion, and ease of maintenance.

Bautista personally used the train simulator at the Malanday depot in Valenzuela City, where the NSCR’s first two train sets are undergoing maintenance.

Equipped with CCTV cameras and Passenger Information Displays, each train set can carry up to 2,288 passengers. DOTr

おすすめ記事

Ex-solon Co claims more than P50b delivered for Marcos, Romualdez

2025/11/26 英字 無料
無料

Seven persons allegedly linked to flood control scandal in custody of authorities

2025/11/26 英字 無料
無料

Interpol issues ''Blue Notice'' vs former solon Co

2025/11/26 英字 無料
無料

BIR suspends field audits, operations including issuing LOAs and MOs ''effective immediately''

2025/11/26 英字 無料
無料

Ambassador Endo Kazuya welcomes the 49th batch of SSEAYP delegates

2025/11/26 英字 無料
無料

DILG gives ex-congressman Co, 17 others until Monday to surrender

2025/11/25 英字 無料
無料