DOTr, JICA and PNR inspect NSCR Balagtas Station and Malanday Depot

2024/7/19 英字

The Department of Transportation (DOTr), Philippine National Railways (PNR), and Japan International Cooperation Agency (JICA) inspected Thursday the North-South Commuter Railway (NSCR) Balagtas Station and Malanday Depot.

The Balagtas station is reported to be 93.67 percent complete, while the Malanday depot stands 72.10 percent complete, as of June.

Transportation Secretary Jaime Bautista first inspected the Balagtas station in Bulacan, which features a roofing membrane known for its resistance to high temperature, chemicals, corrosion, and ease of maintenance.

Bautista personally used the train simulator at the Malanday depot in Valenzuela City, where the NSCR’s first two train sets are undergoing maintenance.

Equipped with CCTV cameras and Passenger Information Displays, each train set can carry up to 2,288 passengers. DOTr

おすすめ記事

Palace says former President Duterte arrested on ICC warrant

2025/3/12 英字 無料
無料

Police trying to bring former President Duterte to a chartered flight: report

2025/3/12 英字 無料
無料

NCRPO goes on heightened alert

2025/3/12 英字 無料
無料

Dry season to start from end of March: Pagasa

2025/3/12 英字 無料
無料

Dengue cases up 73% during January to March period: DOH

2025/3/12 英字 無料
無料

No ICC warrant of arrest yet vs Duterte: spokesperson

2025/3/11 英字 無料
無料