DOTr, JICA and PNR inspect NSCR Balagtas Station and Malanday Depot

2024/7/19 英字

The Department of Transportation (DOTr), Philippine National Railways (PNR), and Japan International Cooperation Agency (JICA) inspected Thursday the North-South Commuter Railway (NSCR) Balagtas Station and Malanday Depot.

The Balagtas station is reported to be 93.67 percent complete, while the Malanday depot stands 72.10 percent complete, as of June.

Transportation Secretary Jaime Bautista first inspected the Balagtas station in Bulacan, which features a roofing membrane known for its resistance to high temperature, chemicals, corrosion, and ease of maintenance.

Bautista personally used the train simulator at the Malanday depot in Valenzuela City, where the NSCR’s first two train sets are undergoing maintenance.

Equipped with CCTV cameras and Passenger Information Displays, each train set can carry up to 2,288 passengers. DOTr

おすすめ記事

No ICC warrant of arrest yet vs Duterte: spokesperson

2025/3/11 英字 無料
無料

Philippines' actions driven by national interest, says DFA

2025/3/11 英字 無料
無料

Marcos names DICT officer-in-charge

2025/3/11 英字 無料
無料

Three fired for alleged ''tanim-bala'' incident at airport

2025/3/11 英字 無料
無料

16 to 19 tropical cyclones expected in 2020: Pagasa

2025/3/11 英字 無料
無料

Duterte to stay in HK for one month as rumors of ICC arrest spread

2025/3/10 英字 無料
無料